Outsourcing – need to outsource
While it may be ideal to
do most of the jobs in-house to ensure strict control over quality of inputs
and processes, outsourcing the work to other agencies may become inescapable,
under circumstances such as:
a. There is no
possibility of getting it done in other Railway workshops with known capacity
and capability for the product.
b. Sudden spurt in the
requirement of components/sub-assemblies far beyond the capacity of the shops
c. Need to optimize and
augment capacity of core shops (assembly shops) resulting in re-deployment of
personnel from non-core to core shops (component to assembly shop) with
consequent capacity reduction ofcomponent shop
d. Introduction of new
material/technology for which skills/capacity/equipment may not be available
within the workshop
e. Standard components
that can be procured from outside or the work outsourced, resulting in lowering
of cost. This is due to economy in scale of production available with the
supplier.
f. Short-term / one time
jobs for which permanent capacity cannot be created within the workshop
g. Need for heavy inputs
of infrastructure not commensurate with the quantum of required by Railways for
its production.
Under these
circumstances, the shop in-charge should decide to opt for outsourcing.
Outsourcing can be from either a unit outside the workshop premises or an
outside agency which will be required to execute the task inside the workshop.
1104. Outsourcing to units outside the workshops.
Components and assemblies
can be outsourced to unit a outside the PU through a system of tendering,
keeping in view the under mentioned guidelines:
a) Decision on
outsourcing shall be taken at the level of the Workshop / Factory In charge,
with Finance Concurrence, except for certain critical components as excluded by
the PHOD wherein criteria for out sourcing as and when needed will be finalised
by HOD of Workshop for Zonal Railways only, in consultation with associate
finance.
b) Pricing guidelines
shall be established on the basis of in-house manufacturing-cost-excluding
overheads and overheads to be added at commercial rates for cost comparison.
1105. Outsourcing or contracting for works within the Railway
Premises.
In case of certain
sub-assemblies, assemblies and critical items, it becomes necessary that
manufacture, assembly and/or testing is carried out inside the Railway premises
by the contracting party due to reasons such as:
a. Need to control of
quality of raw material
b. Facilitate control of
quality of workmanship through stage inspections
c. Specialized
large-scale infrastructure needed for the manufacturing process may not be
available with vendors.
d. Need for investment in
costly specialized equipment, which are otherwise not usable by the vendor for
other general products manufactured by the vendor. Since both these aspects
will inflate his bid price which will ultimately get loaded on the cost of
production. Special tooling required for the job
e. Component/processes
forming part of an assembly line in the ProductionUnit or Workshop.
f. Logistical problems
and disproportionate transportation costs.
1106. While outsourcing within the shop facilities, all safeguards in
Para 1103 shall be ensured. In addition, to avoid contract disputes, care
should be taken to see that following conditions are fulfilled and precautions
taken:
a. Work area for the
contractor to be separated from that of Railway staff
b. Shared machine and
equipment time available to the contractor to be clearly defined to avoid mix
up
c. Wherever raw material
and consumables are to be supplied by the Railway, stock should kept separately
and accounted for.
d. Consumption norms for
raw materials and consumables to be evolved for each item issued to the
contractor by the Railways
e. Documentation to be
signed by both Shop Supervisor and Contractor
f. Electric power, water
and utilities including tools provided by the railways tobe accounted and
documented
g. Control of quality of
workmanship by in process inspection
h. Accountal of scrap /
left over material to be returned by contractor to be accounted and kept
separate
i. Industrial safety
standards as prevailing in the shop shall apply to the contract workers.
j. All relevant legal
provisions and their compliance to be ensured.
Check list for precautions to be taken before contract is awarded
for outsourcing work inside the workshop with outside labour.
Sl
No
|
Precaution To Be Taken
|
Yes`
|
No
|
1
|
Has separate work area for contractor been earmarked
|
|
|
2
|
Has requirement of Railway supplied consumables – like special
electrodes, water, electricity etc. been computed and listed
|
|
|
3
|
Has material requirement for outsourced job been separately
worked out
|
|
|
4
|
Has machine hours for use of Railway equipment for the job been
computed and listed
|
|
|
5
|
whether payment to contract workers is being made through bank,
in a transparent manner
|
|
|
6
|
Have contractor’s workers been issued separate ID
|
|
|
7
|
Is an accounting system in place for contractor supplied items,
raw materials and consumables
|
|
|
8
|
Has workshop supervision been organized to check on the work
|
|
|
9
|
Has the contractor complied with all legal provisions required
under law, for which the Railway has an onus of responsibility
|
|
|
Note: The
answer to all the items is to be ‘yes’, Before outsourcing Contract is awarded.