THE LATEST UNIT COST PER KILOMETER AS ON 31/03/2019
- NEW LINES 8.00 Crores
- GAUGE CONVERSION 3.50 Crores
- DOUBLING 9.60 Crores
- PET (Preliminary Enginerring-cum-
- Traffic Survey 63 Thousands
- Updating PET 27 Thousands
- FLS Final Location Survey 1.80 Lakhs or 2 % of Total sanctioned Estimate
- Preliminary Expenses 9 Lakhs
- Electrification - Route KM 10 Crores
- Electrification - Track KM 1 Crores
THE UNIT COST PER KILOMETER AS ON 31/03/2011
- NEW LINES 5.00 Crores
- GAUGE CONVERSION 5.00 Crores
- DOUBLING 6.00 Crores
- PET (Preliminary Enginerring-cum-
- Traffic Survey 35 Thousands
- Updating PET 15 Thousands
- FLS Final Location Survey 1Lakhs or 2 % of Total sanctioned Estimate
- Preliminary Expenses 5 Lakhs
- Electrification - Route KM 55 Lakhs
- Electrification - Track KM 75 Lakhs
for further clarification please contact Rly Phone 27496 CN/MS;
27114 RE/MS
27114 RE/MS
Sir, May I use the above data for My blog ?
ReplyDelete