Cost and time overruns
1032. Cost and Time overruns:
Cost overruns occur mostly
due to delays in decision making and procurement.
The following steps
should be taken to reduce the lead time and accelerate spending under this plan
head.
a. CMEs should generate a
10 year Master Plan for replacement on age-cum condition basis – indicating
machines to be replaced on chronological basis
for all departments.
b. Proposals to be
carefully thought out and fine tuned. Once a machine is sanctioned, there
should be no road blocks like essentiality certificate etc.
c. While advising Budget
sanctions for new M&Ps, both in Plan Head 41 and 42, the category of the
item (Para above refers) as decided is clearly indicated, so that procurement
action by the concerned agency is organized in time
d. Once the -------
Budget is approved, procurement action for Category A items should be instantly
initiated by COFMOW, without any need for long waits in processing of indents
by the users. Minor clarifications from the Zonal Railways for site details or
other technical requirements can be obtained by COFMOW, in case they are
necessary, through the respective nodal officers of the user Railways.
e. Debits must be passed
on to the Railways or PUs, after the machines are commissioned. For this
purpose COFMOW should be ------ sanctioned a suspense fund as the “Capital at
charge”.
f. Category D items and
category C items wherein dispensation is received from COFMOW should be
directly procured by the concerned user Railway or PU.
g. All M&P indents
should be accompanied by a site drawing, keeping it clear
at the time of indenting
-- except in rare and extraordinary circumstances.
h. Excess over estimates:
COFMOW should make a compendium of rates for all categories of machines, duly
including taxes and duties. This information shall be available in COFMOW’s
interactive portal (www.irmnp.com), to enable the users to indicate realistic
estimates at the time of initiating the proposals, duly avoiding delays in
getting sanctions for Excess over Estimates. Irrespective of the value, excess
over estimates for category A items should be sanctioned by Board and for other
items by the General Manager. SOP should be modified accordingly.
i. The Tender (AT)
documents should
1. Have clearly phrased the warranty clause,
plugging loopholes.
2. Spell out conditions for the terms “Commissioning
Certificate” and “Proving test certificate” unambiguously, binding not only the
consignor but also the consignee. In order to minimize the delays caused by
mismatching creation of various items of an Industrial facility, either through
plan head 41 or through other related plan heads, the following execution
methodology must be considered.
a. Greenfield projects
should preferably be executed through turn-key route. Components of a project
can be grouped into 2 or more sub-projects so that each group in itself is a
complete facility.
b. Likewise facilities of
setting up an assembly line must also be preferably executed through turn-key
route.
c. All individual M&P
items requiring associated facilities such as extensive foundations, sheds,
track linking, substantial power supply etc. must be executed through turn-key
route, as spelt out in para 318 & para 426 stores code and in “Rules for
entering into supply contract”.
d. In Brownfield projects
also where the area has to be vacated for installing new facilities and M&P
may also be executed on turn-key basis.
One single factor that
invariably inflicts heavy “time and cost over runs” undeniably, is inadequate
application of mind at the proposal stage. Quite often, a lump sum cost based
on past experience is assumed for inclusion in the Pink Book. Detailed
estimates are tailored to stay around this ad-hoc figure. More than a year or two
lapses before the various formalities are gone through. The problem gets compounded
if cost escalations manifest in complete revision of estimates.
It is therefore necessary to order a feasibility survey and obtain a Detailed project report
(DPR), particularly in green field projects, such as a new workshop or diesel
shed costing Rs 50 Cr and above. The DPR should bring out:
a. Various options to
meet the demand
b. Investigations for
pre-investment decision by examining these options, including optimization of
existing facilities to decide the best alternative from financial and operating
point of view to make an ideal investment decision.
c. Fairly detailed plans
of the best option so chosen
d. Approx cost in current
prices
e. Expected benefits
f. Project evaluation
which may involve economic analysis, (cf. Para 235-F)or Social Profitability
Analysis, in addition to financial appraisal;
g. Assessment of
deliverables
Sanctioning of mega
projects must therefore not precede a detailed survey, butmust be its natural
corollary. After a Survey is included in the sanctioned Budget, the General
Managers can sanction Survey Estimates costing up to Rs. 5 lakhs.
No comments:
Post a Comment