cost of laying one KM railway line
THE LATEST UNIT COST PER KILOMETER AS ON 31/03/2019
- NEW LINES 8.00 Crores
- GAUGE CONVERSION 3.50 Crores
- DOUBLING 9.60 Crores
- PET (Preliminary Enginerring-cum-
- Traffic Survey 63 Thousands
- Updating PET 27 Thousands
- FLS Final Location Survey 1.80 Lakhs or 2 % of Total sanctioned Estimate
- Preliminary Expenses 9 Lakhs
- Electrification - Route KM 10 Crores
- Electrification - Track KM 1 Crores
THE UNIT COST PER KILOMETER AS ON 31/03/2011
- NEW LINES 5.00 Crores
- GAUGE CONVERSION 5.00 Crores
- DOUBLING 6.00 Crores
- PET (Preliminary Enginerring-cum-
- Traffic Survey 35 Thousands
- Updating PET 15 Thousands
- FLS Final Location Survey 1Lakhs or 2 % of Total sanctioned Estimate
- Preliminary Expenses 5 Lakhs
- Electrification - Route KM 55 Lakhs
- Electrification - Track KM 75 Lakhs
for further clarification please contact Rly Phone 27496 CN/MS;
27114 RE/MS
27114 RE/MS
Saturday, December 21, 2019
Cost and time overruns
Cost and time overruns
1032. Cost and Time overruns:
Cost overruns occur mostly
due to delays in decision making and procurement.
The following steps
should be taken to reduce the lead time and accelerate spending under this plan
head.
a. CMEs should generate a
10 year Master Plan for replacement on age-cum condition basis – indicating
machines to be replaced on chronological basis
for all departments.
b. Proposals to be
carefully thought out and fine tuned. Once a machine is sanctioned, there
should be no road blocks like essentiality certificate etc.
c. While advising Budget
sanctions for new M&Ps, both in Plan Head 41 and 42, the category of the
item (Para above refers) as decided is clearly indicated, so that procurement
action by the concerned agency is organized in time
d. Once the -------
Budget is approved, procurement action for Category A items should be instantly
initiated by COFMOW, without any need for long waits in processing of indents
by the users. Minor clarifications from the Zonal Railways for site details or
other technical requirements can be obtained by COFMOW, in case they are
necessary, through the respective nodal officers of the user Railways.
e. Debits must be passed
on to the Railways or PUs, after the machines are commissioned. For this
purpose COFMOW should be ------ sanctioned a suspense fund as the “Capital at
charge”.
f. Category D items and
category C items wherein dispensation is received from COFMOW should be
directly procured by the concerned user Railway or PU.
g. All M&P indents
should be accompanied by a site drawing, keeping it clear
at the time of indenting
-- except in rare and extraordinary circumstances.
h. Excess over estimates:
COFMOW should make a compendium of rates for all categories of machines, duly
including taxes and duties. This information shall be available in COFMOW’s
interactive portal (www.irmnp.com), to enable the users to indicate realistic
estimates at the time of initiating the proposals, duly avoiding delays in
getting sanctions for Excess over Estimates. Irrespective of the value, excess
over estimates for category A items should be sanctioned by Board and for other
items by the General Manager. SOP should be modified accordingly.
i. The Tender (AT)
documents should
1. Have clearly phrased the warranty clause,
plugging loopholes.
2. Spell out conditions for the terms “Commissioning
Certificate” and “Proving test certificate” unambiguously, binding not only the
consignor but also the consignee. In order to minimize the delays caused by
mismatching creation of various items of an Industrial facility, either through
plan head 41 or through other related plan heads, the following execution
methodology must be considered.
a. Greenfield projects
should preferably be executed through turn-key route. Components of a project
can be grouped into 2 or more sub-projects so that each group in itself is a
complete facility.
b. Likewise facilities of
setting up an assembly line must also be preferably executed through turn-key
route.
c. All individual M&P
items requiring associated facilities such as extensive foundations, sheds,
track linking, substantial power supply etc. must be executed through turn-key
route, as spelt out in para 318 & para 426 stores code and in “Rules for
entering into supply contract”.
d. In Brownfield projects
also where the area has to be vacated for installing new facilities and M&P
may also be executed on turn-key basis.
One single factor that
invariably inflicts heavy “time and cost over runs” undeniably, is inadequate
application of mind at the proposal stage. Quite often, a lump sum cost based
on past experience is assumed for inclusion in the Pink Book. Detailed
estimates are tailored to stay around this ad-hoc figure. More than a year or two
lapses before the various formalities are gone through. The problem gets compounded
if cost escalations manifest in complete revision of estimates.
It is therefore necessary to order a feasibility survey and obtain a Detailed project report
(DPR), particularly in green field projects, such as a new workshop or diesel
shed costing Rs 50 Cr and above. The DPR should bring out:
a. Various options to
meet the demand
b. Investigations for
pre-investment decision by examining these options, including optimization of
existing facilities to decide the best alternative from financial and operating
point of view to make an ideal investment decision.
c. Fairly detailed plans
of the best option so chosen
d. Approx cost in current
prices
e. Expected benefits
f. Project evaluation
which may involve economic analysis, (cf. Para 235-F)or Social Profitability
Analysis, in addition to financial appraisal;
g. Assessment of
deliverables
Sanctioning of mega
projects must therefore not precede a detailed survey, butmust be its natural
corollary. After a Survey is included in the sanctioned Budget, the General
Managers can sanction Survey Estimates costing up to Rs. 5 lakhs.
Maintenance of civil and electrical infrastructure in workshops:
Maintenance of civil and electrical infrastructure in workshops:
Timely inputs of
Maintenance can avoid major investments for the fixed infrastructure of
Workshops through Works Programme. Also as per provisions of factory act, the
occupier is expected to ensure that the plant and systems are maintained so
that these are safe and cause no health hazards.
a. To enable the occupier to
discharge the duties without compromising on health and safety, it is necessary
that separate funds are earmarked for repair and maintenance of civil and electrical
infrastructure of workshops. For maintenance of civil engineering infrastructure
separate provision of funds in Detailed Heads 431 (Workshops) and 433 (Stores)
under Revenue Demand 4-430 should be given. Similar exclusive provision of
funds for maintenance of infrastructure for electrical services should be done.
Funds should be communicated by zonal Railway headquarters to the workshops
under the relevant revenue heads, to be spent with the specific approval/
sanction of the workshop in-charge.
b. In respect of funds
for maintenance of civil and electrical infrastructure forworkshops, all
budgetary reviews/ estimates i.e. August Review, R.E., F.M. and B.E. should be
done by workshops depending on the need to maintain workshop infrastructure by
CWM.
c. The workshop Finance
shall act as the Associate Finance for all infrastructure maintenance contract
matters related to the workshop.
d. The process of
estimation and tendering for works should be done/coordinated by workshop Civil
/ Electrical Engineer.
Capital / Unit exchange spares.
Capital /
Unit exchange spares.
Certain items of spares
for diesel locos, diesel rail cars, electric locos, Break Down Cranes and
EMU/MEMU stock which are not in the nature of consumable stores but intended to accelerate repairs are identified
as capital/unit exchange spares chargeable to Capital directly. In view of the
increase in the cost of locomotives in the past few years, obsolescence in the
current list of items of capital/unit exchange spares, improvement in the
degree of reliability of major components/assembly kept as spares, utility of each
component by itself or as a part of a major assembly, lead time for the
procurement & nature of the item and whether kept as stock items or not,
the monetary limit for
capitalization of spares which are procured through IRSP is fixed at a certain
level by Railway Board, which shall be revised periodically according
to an appropriate
formula, taking inflation into account. Low-cost unit exchange Spares with unit
cost below such monetory limit is not included in the proposal for IRSP, but
procured through Stock/Non-stock indents allocating the expenditure to Revenue.
Lists of capital/unit
exchange spares along with their percentage on the holding as well as the
provision/ share between workshops and sheds to be maintained, shall be advised
by Railway Board periodically. The list should be for restricted number of items
only, which are very critical rolling stock sub-assemblies, having longer lead
for procurement and the repair practice in workshops is cumbersome/ time
consuming, affecting the cycle time of repair of rolling stock in the
workshops.
Note: While Items with
unit cost below the threshold monetory limit stipulated by Railway Board may
not be generally included as capital spare in the RSP, same does not imply that
the items costing above the threshold monetory limit are to be treated only as
Capital Spares same can be allowed to be purchased under revenue, subject to exigencies
and emergent situations.