cost of laying one KM railway line



THE LATEST UNIT COST PER KILOMETER AS ON 31/03/2019
  • NEW LINES                                 8.00 Crores
  • GAUGE CONVERSION             3.50 Crores
  • DOUBLING                                 9.60 Crores
  • PET (Preliminary Enginerring-cum-
  • Traffic Survey                              63 Thousands
  • Updating PET                               27  Thousands
  • FLS Final Location Survey          1.80 Lakhs or 2 % of Total sanctioned Estimate
  • Preliminary Expenses                 9 Lakhs         
  • Electrification - Route KM        10 Crores 
  • Electrification - Track KM        1 Crores  


THE UNIT COST PER KILOMETER AS ON 31/03/2011
  • NEW LINES                                 5.00 Crores
  • GAUGE CONVERSION             5.00 Crores
  • DOUBLING                                 6.00 Crores
  • PET (Preliminary Enginerring-cum-
  • Traffic Survey                              35 Thousands
  • Updating PET                               15  Thousands
  • FLS Final Location Survey         1Lakhs or 2 % of Total sanctioned Estimate
  • Preliminary Expenses                 5 Lakhs         
  • Electrification - Route KM        55 Lakhs
  • Electrification - Track KM        75 Lakhs
for further clarification please contact Rly Phone 27496 CN/MS; 
27114 RE/MS

Saturday, December 21, 2019

Cost and time overruns



Cost and time overruns
1032. Cost and Time overruns:

Cost overruns occur mostly due to delays in decision making and procurement.
The following steps should be taken to reduce the lead time and accelerate spending under this plan head.
a. CMEs should generate a 10 year Master Plan for replacement on age-cum condition basis – indicating machines to be replaced on chronological basis
for all departments.
b. Proposals to be carefully thought out and fine tuned. Once a machine is sanctioned, there should be no road blocks like essentiality certificate etc.
c. While advising Budget sanctions for new M&Ps, both in Plan Head 41 and 42, the category of the item (Para above refers) as decided is clearly indicated, so that procurement action by the concerned agency is organized in time
d. Once the ------- Budget is approved, procurement action for Category A items should be instantly initiated by COFMOW, without any need for long waits in processing of indents by the users. Minor clarifications from the Zonal Railways for site details or other technical requirements can be obtained by COFMOW, in case they are necessary, through the respective nodal officers of the user Railways.
e. Debits must be passed on to the Railways or PUs, after the machines are commissioned. For this purpose COFMOW should be ------ sanctioned a suspense fund as the “Capital at charge”.
f. Category D items and category C items wherein dispensation is received from COFMOW should be directly procured by the concerned user Railway or PU.
g. All M&P indents should be accompanied by a site drawing, keeping it clear
at the time of indenting -- except in rare and extraordinary circumstances.
h. Excess over estimates: COFMOW should make a compendium of rates for all categories of machines, duly including taxes and duties. This information shall be available in COFMOW’s interactive portal (www.irmnp.com), to enable the users to indicate realistic estimates at the time of initiating the proposals, duly avoiding delays in getting sanctions for Excess over Estimates. Irrespective of the value, excess over estimates for category A items should be sanctioned by Board and for other items by the General Manager. SOP should be modified accordingly.
i. The Tender (AT) documents should
1. Have clearly phrased the warranty clause, plugging loopholes.
2. Spell out conditions for the terms “Commissioning Certificate” and “Proving test certificate” unambiguously, binding not only the consignor but also the consignee. In order to minimize the delays caused by mismatching creation of various items of an Industrial facility, either through plan head 41 or through other related plan heads, the following execution methodology must be considered.
a. Greenfield projects should preferably be executed through turn-key route. Components of a project can be grouped into 2 or more sub-projects so that each group in itself is a complete facility.
b. Likewise facilities of setting up an assembly line must also be preferably executed through turn-key route.
c. All individual M&P items requiring associated facilities such as extensive foundations, sheds, track linking, substantial power supply etc. must be executed through turn-key route, as spelt out in para 318 & para 426 stores code and in “Rules for entering into supply contract”.
d. In Brownfield projects also where the area has to be vacated for installing new facilities and M&P may also be executed on turn-key basis.

One single factor that invariably inflicts heavy “time and cost over runs” undeniably, is inadequate application of mind at the proposal stage. Quite often, a lump sum cost based on past experience is assumed for inclusion in the Pink Book. Detailed estimates are tailored to stay around this ad-hoc figure. More than a year or two lapses before the various formalities are gone through. The problem gets compounded if cost escalations manifest in complete revision of estimates.
It is therefore necessary to order a feasibility survey and obtain a Detailed project report (DPR), particularly in green field projects, such as a new workshop or diesel shed costing Rs 50 Cr and above. The DPR should bring out:
a. Various options to meet the demand
b. Investigations for pre-investment decision by examining these options, including optimization of existing facilities to decide the best alternative from financial and operating point of view to make an ideal investment decision.
c. Fairly detailed plans of the best option so chosen
d. Approx cost in current prices
e. Expected benefits
f. Project evaluation which may involve economic analysis, (cf. Para 235-F)or Social Profitability Analysis, in addition to financial appraisal;
g. Assessment of deliverables
Sanctioning of mega projects must therefore not precede a detailed survey, butmust be its natural corollary. After a Survey is included in the sanctioned Budget, the General Managers can sanction Survey Estimates costing up to Rs. 5 lakhs.


Maintenance of civil and electrical infrastructure in workshops:


Maintenance of civil and electrical infrastructure in workshops:
Timely inputs of Maintenance can avoid major investments for the fixed infrastructure of Workshops through Works Programme. Also as per provisions of factory act, the occupier is expected to ensure that the plant and systems are maintained so that these are safe and cause no health hazards.
a. To enable the occupier to discharge the duties without compromising on health and safety, it is necessary that separate funds are earmarked for repair and  maintenance of civil and electrical infrastructure of workshops. For maintenance of civil engineering infrastructure separate provision of funds in Detailed Heads 431 (Workshops) and 433 (Stores) under Revenue Demand 4-430 should be given. Similar exclusive provision of funds for maintenance of infrastructure for electrical services should be done. Funds should be communicated by zonal Railway headquarters to the workshops under the relevant revenue heads, to be spent with the specific approval/ sanction of the workshop in-charge.
b. In respect of funds for maintenance of civil and electrical infrastructure forworkshops, all budgetary reviews/ estimates i.e. August Review, R.E., F.M. and B.E. should be done by workshops depending on the need to maintain workshop infrastructure by CWM.
c. The workshop Finance shall act as the Associate Finance for all infrastructure maintenance contract matters related to the workshop.
d. The process of estimation and tendering for works should be done/coordinated by workshop Civil / Electrical Engineer.

Capital / Unit exchange spares.


Capital / Unit exchange spares.
Certain items of spares for diesel locos, diesel rail cars, electric locos, Break Down Cranes and EMU/MEMU stock which are not in the nature of consumable stores but  intended to accelerate repairs are identified as capital/unit exchange spares chargeable to Capital directly. In view of the increase in the cost of locomotives in the past few years, obsolescence in the current list of items of capital/unit exchange spares, improvement in the degree of reliability of major components/assembly kept as spares, utility of each component by itself or as a part of a major assembly, lead time for the procurement & nature of the item and whether kept as stock items or not,
the monetary limit for capitalization of spares which are procured through IRSP is fixed at a certain level by Railway Board, which shall be revised periodically according
to an appropriate formula, taking inflation into account. Low-cost unit exchange Spares with unit cost below such monetory limit is not included in the proposal for IRSP, but procured through Stock/Non-stock indents allocating the expenditure to Revenue.
Lists of capital/unit exchange spares along with their percentage on the holding as well as the provision/ share between workshops and sheds to be maintained, shall be advised by Railway Board periodically. The list should be for restricted number of items only, which are very critical rolling stock sub-assemblies, having longer lead for procurement and the repair practice in workshops is cumbersome/ time consuming, affecting the cycle time of repair of rolling stock in the workshops.

Note: While Items with unit cost below the threshold monetory limit stipulated by Railway Board may not be generally included as capital spare in the RSP, same does not imply that the items costing above the threshold monetory limit are to be treated only as Capital Spares same can be allowed to be purchased under revenue, subject to exigencies and emergent situations.