Wednesday, March 28, 2012

UNIT COST OF NEW LINES etc


THE LATEST UNIT COST PER KILOMETER AS ON 31/03/2011
  • NEW LINES                                 5.00 Crores
  • GAUGE CONVERSION             5.00 Crores
  • DOUBLING                                 6.00 Crores
  • PET (Preliminary Enginerring-cum-
  • Traffic Survey                              35 Thousands
  • Updating PET                               15  Thousands
  • FLS Final Location Survey         1Lakhs or 2 % of Total sanctioned Estimate
  • Preliminary Expenses                 5 Lakhs         
  • Electrification - Route KM        55 Lakhs
  • Electrification - Track KM        75 Lakhs
for further clarification please contact Rly Phone 27496 CN/MS; 
27114 RE/MS

Monday, March 19, 2012

Wednesday, February 29, 2012

Monday, February 27, 2012

FUNCTIONS OF DIVISIONAL ACCOUNTANTS





 FUNCTIONS OF D IVISIONALACCOUNTANT


q  as an accountant he should check arithmetical accuracy of all vouchers fully and compile the accounts of the divn in accordance with the prescribed rules and form the data supplied to him by the sub divns
q  As representative of A/c dept he should apply all the checks which is normally applied in the A/c office to the initial a/cs vouchers and other documents
q  As financial assistant,  he should assist the executive in matters relating to a/c s , budget estimates and to the operation of  financial rules generally
q   the relation between the DEN and D A is that of a Sub divisional officer and the DEN. The DEN is supposed to consult the DA in all matters involving a/cs,. Finance or budget. The DEN should see that the DA is given fullest opportunity of becoming conversant with all sanctions and orders, estimates and proposals. 

The DA is considered as the head of the office establishment of the DEN. While checking accounts and returns whenever the DA finds any irregularity, he should bring to the notice of DEN. 

If DEN differs from the views of DA he records his orders and the same should be carried out. In such cases DA should maintain a register as DA’s Internal Check Register and enter the same with full details in the register and obtain the remarks of DEN therein. This register is put up to any visiting officer for information

The DA should not however, be made responsible for any cash transaction except emergent cases not exceeding four months.
The DA should maintain cordial relationship not only with DEN but also with all other sub divisional officers and also educate the office staff and subordinates about proper maintenance of records, submission of accounts returns, preparation of budget etc

In the open line divisions also a SO (Works) is posted under the DEN designated as Works Accountant. The functions are the same as DA. However, he is not considered as he head of divisional works branch but will be the head of works accounts section. 

The DA is considered as the head of the office establishment of the DEN. While checking accounts and returns whenever the DA finds any irregularity, he should bring to the notice of DEN. If DEN differs from the views of DA he records his orders and the same should be carried out. In such cases DA should maintain a register as DA’s Internal Check Register and enter the same with full details in the register and obtain the remarks of DEN therein. This register is put up to any visiting officer for information

The DA should not however, be made responsible for any cash transaction except emergent cases not exceeding four months.
The DA should maintain cordial relationship not only with DEN but also with all other sub divisional officers and also educate the office staff and subordinates about proper maintenance of records, submission of accounts returns, preparation of budget etc

In the open line divisions also a SO ( Works) is posted under the DEN designated as Works Accountant. The functions are the same as DA. However, he is not considered as he head of divisional works branch  but will be the head of works accounts section.  

MATERIAL AT SITE ACCOUNTS


  1. For works estimated to cost each Rs 1 lakhs or Rs 3 lakhs for relaying or track renewal work in relaxation of the limit of Rs 25000/-.
  2. for stores not used up immediately
  3. suspense head – on receipt of materials  is debited with the cost of stores and is credited with issued of materials for work
  4. daily record of such material in form E 1737  materials obtained for work on receipt are entered under with quantity, issued note and reference – Receipts: issues of stores for consumption, the date, quantity, sub head charged are recorded under – Issues . Materials issued but surplus – Minus Issues
  5. materials released from the work are separately recorded as receipts with date, quantity on their utilization of the works shown as issues Materials retuned to stores transferred or otherwise deposed of is shown as minus receipts
  6. works costing  more than Rs 1 lakh to Rs 3 lakhs for relaying or track renewal works- monthly Return is sent containing only those items for which there have been any receipts or issue transactions during the month.
  7. the monthly MAS a/c returns may be followed by a complete MAS a/c return for all the items of each quarter June, September, December & March on the basis of monthly returns from sub ordinates, the Divisional Officers prepare monthly adjustments get them approved by DEN and AO for necessary adjustment
  8. periodical verification by the executive in charge for works costing  more than Rs 1 lakh to Rs 3 lakhs for relaying or track renewal a. P Way material b. other MAS which can be readily operated and distinguished from any of the description but by a different category all items verified at least once in a year.
A certificate that such verification has been carried out should together with a note as to whether or not the materials were found to be duly depreciated, be furnished on the MAS returns this is in addition to stock verification.
At the end of every financial year the AO prepares a schedule of MAS balances of works of Rs 1 lakh to Rs 3 lakhs for relaying or track renewal and review in consultation with the executive.
At the end of every month, an excess materials return should be prepared in the prescribed proforma in respect of all the completed works. 
These returns should show separately for materials obtained and material released, the numerical balance only of MAS i.e. those that have neither have been consumed on the work nor returned to stores, transferred or otherwise disposed of and the ate of completion of the work to which they relate. If the excess materials cannot be utilized in some other work they should be returned to stores.

SENSITIVITY ANALYSIS



SENSITIVITY ANALYSIS
                         D X Gnanaraj AFA/W/PER

1.   simplest of handling risks
2.   magnitude in the ROR by small change in the components of which are uncertain
3.   selct variable –whose estimated values may contain significant errors or elements of uncertainty
4.   key variables are – cost, price, project life, market share etc

Advantage:
1.   identify crucial variables that makes greatest impact in the NPV of the project
2.   graphical presentation – better visual appeal
3.   by confining SA to adverse changes in the variable that can be reasonably expected to occur one can obtain range of NPV that can be reasonably anticipated
4.   knowledge is helpful for making decisions
   5. Graph

Railways Risk Factors:
1.   land - delay in acquisition – litigation
2.   earth work availability of sand
3.   soil condition – geographical factors –weak/loose Eg TEN-NGC line due to weak soil
4.   alignment due to local or popular demand Eg KRCL in Madgaon line in Goa State
5.   availability of sleepers – wooden/ Pre Stressed Concrete Sleepers – snags in production- ban on wooden sleepers as environmental policy of the Govt
6.   availability of rails – change in the production pattern of the steel mills – delay in production- change in the Govt policy
7.   estimated earnings – net production of commodities short fall in projected and traffic due to climatic and natural causes – import and export potential
8.   delay in rolling stock in ordered quantity Eg Hassan – Mangalore line for transport of ore to Port of Mangalore diverted to road
9.   cost and time over runs – likely delay due to paucity of funds/allotment