THE LATEST UNIT COST PER KILOMETER AS ON 31/03/2011
  • NEW LINES                                 5.00 Crores
  • GAUGE CONVERSION             5.00 Crores
  • DOUBLING                                 6.00 Crores
  • PET (Preliminary Enginerring-cum-
  • Traffic Survey                              35 Thousands
  • Updating PET                               15  Thousands
  • FLS Final Location Survey         1Lakhs or 2 % of Total sanctioned Estimate
  • Preliminary Expenses                 5 Lakhs         
  • Electrification - Route KM        55 Lakhs
  • Electrification - Track KM        75 Lakhs